08/10/2026 | Facilities Master Planning Committee Update
- Outside work continues on getting the ground prepped for the foundation slab pour for the Adoration Chapel
- Temporary wall has been placed in the Narthex and side hallway
- Demolition has started in the meeting rooms
- 95% of church basement is framed out - plumbing and electrical continues
- Framing, electrical and plumbing almost complete in school basement
- HVAC work continues in school basement