Week of October 5
10/05/2026 | Facilities Master Planning Committee Update- Exterior sheathing and window blocking for Adoration Chapel and addition
- If last set of doors arrive, drywall and doorways to be completed in both school and church basements
- Prime and first coat of paint in church basement
Week of September 28
09/28/2026 | Facilities Master Planning Committee Update- Finishing exterior framing on addition and Adoration Chapel
- Continued mudding/taping/sanding of walls in the church basement
- Flooring and ceiling grid work in progress in school basement
Week of September 19
09/19/2026 | Facilities Master Planning Committee UpdateWeeks of September 14 & 21
09/14/2026 | Facilities Master Planning Committee UpdateSchool basement:
- Paint 90% complete
- Ceiling grid is in progress
- Flooring to start
- Awaiting a few doors/doorframes to arrive to complete sheetrock and paint
Church basement:
- Sheetrock began this week
- continued HVAC & above ceiling electrical
Adoration Chapel/Addition:
- Trusses arriving; install next week (you'll begin to really see the shape of the Adoration Chapel)
- Continued plumbing work in the addition
Week of September 3
09/03/2026 | Facilities Master Planning Committee UpdateWeeks of August 31 & September 7
08/31/2026 | Facilities Master Planning Committee UpdateAdoration Chapel/Meeting Hall: Progress is being made on the structural steel and walls. You should continue to see progress as you drive in from Johnson Dr!!
School Basement: Sheetrock has been hung and prime and painting have started!!
Church Basement: Sheetrock begins next week!!!
Week of August 24
08/24/2026 | Facilities Master Planning Committee UpdateStructural Steel has been delivered.
Depending on weather, should see beams being installed and the Adoration Chapel forming and the meeting room expansion
School Basement:
- Electrical inspection passed
- Insulation and drywall currently being installed
Church Basement:
- HVAC install has begun
- Getting ready for electrical inspections
Week of August 20
08/20/2026 | Facilities Master Planning Committee UpdateWeeks of August 10 and August 17
08/10/2026 | Facilities Master Planning Committee Update- Outside work continues on getting the ground prepped for the foundation slab pour for the Adoration Chapel
- Temporary wall has been placed in the Narthex and side hallway
- Demolition has started in the meeting rooms
- 95% of church basement is framed out - plumbing and electrical continues
- Framing, electrical and plumbing almost complete in school basement
- HVAC work continues in school basement