Week of November 11
11/11/2026 | Facilities Master Planning Committee UpdateWeek of November 2
11/02/2026 | Facilities Master Planning Committee UpdateWeek of October 5
10/05/2026 | Facilities Master Planning Committee Update- Exterior sheathing and window blocking for Adoration Chapel and addition
- If last set of doors arrive, drywall and doorways to be completed in both school and church basements
- Prime and first coat of paint in church basement
Week of September 28
09/28/2026 | Facilities Master Planning Committee Update- Finishing exterior framing on addition and Adoration Chapel
- Continued mudding/taping/sanding of walls in the church basement
- Flooring and ceiling grid work in progress in school basement
Week of September 19
09/19/2026 | Facilities Master Planning Committee UpdateWeeks of September 14 & 21
09/14/2026 | Facilities Master Planning Committee UpdateSchool basement:
- Paint 90% complete
- Ceiling grid is in progress
- Flooring to start
- Awaiting a few doors/doorframes to arrive to complete sheetrock and paint
Church basement:
- Sheetrock began this week
- continued HVAC & above ceiling electrical
Adoration Chapel/Addition:
- Trusses arriving; install next week (you'll begin to really see the shape of the Adoration Chapel)
- Continued plumbing work in the addition