Week of September 28
09-28-2026 Facilities Master Planning Committee Update
Finishing exterior framing on addition and Adoration Chapel
Continued mudding/taping/sanding of walls in the church basement
Flooring and ceiling grid work in progress in school basement
VIDEO
Week of September 19
09-19-2026 Facilities Master Planning Committee Update
VIDEO
Weeks of September 14 & 21
09-14-2026 Facilities Master Planning Committee Update
School basement:
Paint 90% complete
Ceiling grid is in progress
Flooring to start
Awaiting a few doors/doorframes to arrive to complete sheetrock and paint
Church basement:
Sheetrock began this week
continued HVAC & above ceiling electrical
Adoration Chapel/Addition:
Trusses arriving; install next week (you'll begin to really see the shape of the Adoration Chapel)
Continued plumbing work in the addition
Week of September 3
09-03-2026 Facilities Master Planning Committee Update
VIDEO
Weeks of August 31 & September 7
08-31-2026 Facilities Master Planning Committee Update
Adoration Chapel/Meeting Hall: Progress is being made on the structural steel and walls. You should continue to see progress as you drive in from Johnson Dr!!
School Basement: Sheetrock has been hung and prime and painting have started!!
Church Basement: Sheetrock begins next week!!!
Week of August 24
08-24-2026 Facilities Master Planning Committee Update
Structural Steel has been delivered. Depending on weather, should see beams being installed and the Adoration Chapel forming and the meeting room expansion
School Basement:
Electrical inspection passed
Insulation and drywall currently being installed
Church Basement:
HVAC install has begun
Getting ready for electrical inspections
READ MORE
Week of August 20
08-20-2026 Facilities Master Planning Committee Update
VIDEO
Weeks of August 10 and August 17
08-10-2026 Facilities Master Planning Committee Update
Outside work continues on getting the ground prepped for the foundation slab pour for the Adoration Chapel
Temporary wall has been placed in the Narthex and side hallway
Demolition has started in the meeting rooms
95% of church basement is framed out - plumbing and electrical continues
Framing, electrical and plumbing almost complete in school basement
HVAC work continues in school basement
READ MORE
Week of August 6
08-06-2026 Facilities Master Planning Committee Update
VIDEO