Week of August 24
08-24-2026Facilities Master Planning Committee Update
Structural Steel has been delivered.
Depending on weather, should see beams being installed and the Adoration Chapel forming and the meeting room expansion
School Basement:
- Electrical inspection passed
- Insulation and drywall currently being installed
Church Basement:
- HVAC install has begun
- Getting ready for electrical inspections
READ MORE
Weeks of August 10 and August 17
08-10-2026Facilities Master Planning Committee Update
- Outside work continues on getting the ground prepped for the foundation slab pour for the Adoration Chapel
- Temporary wall has been placed in the Narthex and side hallway
- Demolition has started in the meeting rooms
- 95% of church basement is framed out - plumbing and electrical continues
- Framing, electrical and plumbing almost complete in school basement
- HVAC work continues in school basement
READ MORE