Week of November 11

11/11/2026  |  Facilities Master Planning Committee Update

Week of November 2

11/02/2026  |  Facilities Master Planning Committee Update

Week of October 5

10/05/2026  |  Facilities Master Planning Committee Update
  • Exterior sheathing and window blocking for Adoration Chapel and addition
  • If last set of doors arrive, drywall and doorways to be completed in both school and church basements
  • Prime and first coat of paint in church basement

Week of September 28

09/28/2026  |  Facilities Master Planning Committee Update
  • Finishing exterior framing on addition and Adoration Chapel
  • Continued mudding/taping/sanding of walls in the church basement
  • Flooring and ceiling grid work in progress in school basement

Week of September 19

09/19/2026  |  Facilities Master Planning Committee Update

Weeks of September 14 & 21

09/14/2026  |  Facilities Master Planning Committee Update

School basement:

  • Paint 90% complete
  • Ceiling grid is in progress
  • Flooring to start
  • Awaiting a few doors/doorframes to arrive to complete sheetrock and paint

Church basement:

  • Sheetrock began this week
  • continued HVAC & above ceiling electrical

Adoration Chapel/Addition:

  • Trusses arriving; install next week (you'll begin to really see the shape of the Adoration Chapel)
  • Continued plumbing work in the addition

Week of September 3

09/03/2026  |  Facilities Master Planning Committee Update