Week of September 28

09-28-2026Facilities Master Planning Committee Update
  • Finishing exterior framing on addition and Adoration Chapel
  • Continued mudding/taping/sanding of walls in the church basement
  • Flooring and ceiling grid work in progress in school basement

Week of September 19

09-19-2026Facilities Master Planning Committee Update

Weeks of September 14 & 21

09-14-2026Facilities Master Planning Committee Update

School basement:

  • Paint 90% complete
  • Ceiling grid is in progress
  • Flooring to start
  • Awaiting a few doors/doorframes to arrive to complete sheetrock and paint

Church basement:

  • Sheetrock began this week
  • continued HVAC & above ceiling electrical

Adoration Chapel/Addition:

  • Trusses arriving; install next week (you'll begin to really see the shape of the Adoration Chapel)
  • Continued plumbing work in the addition

Week of September 3

09-03-2026Facilities Master Planning Committee Update

Weeks of August 31 & September 7

08-31-2026Facilities Master Planning Committee Update

Adoration Chapel/Meeting Hall: Progress is being made on the structural steel and walls. You should continue to see progress as you drive in from Johnson Dr!!

School Basement: Sheetrock has been hung and prime and painting have started!!

Church Basement: Sheetrock begins next week!!!

Week of August 24

08-24-2026Facilities Master Planning Committee Update

Structural Steel has been delivered.
Depending on weather, should see beams being installed and the Adoration Chapel forming and the meeting room expansion

School Basement:

  • Electrical inspection passed
  • Insulation and drywall currently being installed

Church Basement:

  • HVAC install has begun
  • Getting ready for electrical inspections
READ MORE

Week of August 20

08-20-2026Facilities Master Planning Committee Update

Weeks of August 10 and August 17

08-10-2026Facilities Master Planning Committee Update
  • Outside work continues on getting the ground prepped for the foundation slab pour for the Adoration Chapel
  • Temporary wall has been placed in the Narthex and side hallway
  • Demolition has started in the meeting rooms
  • 95% of church basement is framed out - plumbing and electrical continues
  • Framing, electrical and plumbing almost complete in school basement
  • HVAC work continues in school basement
READ MORE

Week of August 6

08-06-2026Facilities Master Planning Committee Update